Contractor's design portion
The contractor’s designed portion (sometimes referred to as 'contractor's design portion' or CDP) is associated with JCT construction contracts. It is an agreement for the contractor to design specific parts of the works. The contractor may in turn sub-contract this design work to specialist sub-contractors. This should not be confused with design and build contracts where the contractor is appointed to design the whole of the works.
Until 2005, the JCT Standard Building Contract had a contractor’s designed portion supplement for use where the appointed contractor was required to design specific parts of the works. This provision has now been incorporated into the main contract, but a separate sub-contractor design agreement is available where the main contractor is to design specific parts of the works and a sub-contractor is to design part or all of the sub-contract works.
The JCT Intermediate Building Contract still has a separate contractor’s design agreement, as well as a sub-contractor's design agreement. The JCT Minor Works Contract has a ‘with contractor’s design’ option and a separate sub-contract with sub-contractor’s design.
The client’s requirements for contractor's design will generally be set out in the tender documents as ‘Employer’s Requirements’ in response to which the contractor will submit ‘Contractor’s Proposals’.
Contractor’s design may be used with a Pre-Construction Services Agreement or Pre-Construction Services Agreement (Specialist) to provide early consultancy services to the project before the main construction contract commences.
Often, the portion of design left to the contractor is the detailing work undertaken by specialist manufactures and installers. The main contractor has responsibility for managing the procurement of its specialist sub-contractor’s design in an orderly fashion and to an agreed programme so it can be approved by the client’s design team (who within their conditions of engagement avoid liability for specialist design).
The main contractor also has to ensure that various specialist sub-contractors under its control co-ordinate their emerging designs with each other. For instance the services sub-contractors need to know both the grid system and position of fixings for a suspended ceiling and likewise the ceiling sub-contractor needs to know details of plant above ceilings which require maintenance access. To carry out this management function 'design managers' have become a regular addition to the main contractor’s project staff.
The main contractor may be given the responsibility for ensuring that its sub-contractor’s design is submitted for and obtains building regulations approval. The client’s design team will usually submit specialist design to the planning authorities when necessary to satisfy planning conditions since it is generally the design team’s responsibility to obtain full planning consent.
Design consultant’s need to judge how far to take their design before handing over its completion to specialists. Furthermore it must be made abundantly clear exactly what the specialist has to design within the work section. A performance specification must describe quality both in terms of function and form, bearing in mind that contractors tendering in competition will respond with the cheapest option available to meet the specification.
The use of a sub-contractor design approval procedures to improve what was tendered has been the source of back door variations and many contractual disputes in relation to cost and/or delay. On the other hand it is a waste of designers’ resources and time to develop the design of systems that may or may not be used. Closed specifications reduce options in the specialist market and this is not in the best interests of the client.
It is sensible for the main tender documents to ask for a sub-contractor design programme to be submitted by the main contractor within a certain period after the contract has been placed. This should track specialist design, the approval process, manufacture and installation and fit into the overall contract programme. It is reasonable for the design team to insist on an even workload of sub-contractor drawing submittals so it can balance its resources in relation to the comment and approval process.
The introduction of building information modelling (BIM) is likely to have a profound effect on contractor's design. If at the time of the main contractor's appointment, a fully-integrated and collaborative building model has been prepared, it is unlikely that this will simply be handed over to the main contractor.
The model is more likely to remain under the management of the client's design team. Whoever is managing the model will be the party that has to manage the collective input of specialist designers. The main contractor’s role in this process could therefore become redundant, which is not satisfactory under the current terms of contractor's design agreements because it effectively means the designers would be controlling activities of the main contractor’s sub-contractors.
However, the main contractor carries the risk of a fixed price and meeting the contract completion date. For this and for programme reasons, contractor's design in the way that we know it now could become a thing of the past. In any case the advent of BIM is likely to alter the timing of the inclusion of specialist design so it takes place in the pre-construction design stage rather than in the construction stage.
Consequently the design team will work on the design with specialists in the pre-construction stage and insist that the tendering contractors adopt the specialist and its design as part of the tender offer. So the scope of specialist work, its price and programme will be included within the main contractor's bid.
The main contractor’s tender documents will also give the main contractor the choice of seeking alternative sub-contractors thus avoiding the legal problems associated with nominated sub-contractors when the courts judged that a main contractor was not liable for the performance of a sub-contractor forced upon it by the client or its agents.
[edit] Related articles on Designing Buildings
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
We are the leading warm Roof Construction Specialists in London. If you are looking for experienced warm roof Construction contractors that provide high-quality services and do fast roof installation, then don’t move further, we are the detached house loft conversion company that you need. Just contact us by giving us a query or call us at 07939 087397.
We have many years of great experience in construction and also working with all kinds of customers across London. Our customers are happy with our dream services and our quality of work.
Call us at Mobile: 0793 9087 397, Office: 0162 8472 013
Write us Email at:[email protected]